articles Ratings /ratings/en/research/articles/200219-foresight-is-2020-tailwinds-for-u-s-offshore-expansion-11355809 content esgSubNav
In This List
COMMENTS

The Energy Transition: Foresight Is 2020: Tailwinds For U.S. Offshore Expansion

COMMENTS

Private Markets Monthly, December 2024: Private Credit Trends To Watch In 2025

COMMENTS

Sustainable Finance FAQ: The Rise Of Green Equity Designations

COMMENTS

Instant Insights: Key Takeaways From Our Research

COMMENTS

CreditWeek: How Will COP29 Agreements Support Developing Economies?


The Energy Transition: Foresight Is 2020: Tailwinds For U.S. Offshore Expansion

Legend has it that in picking the name for his rock band, The Doors, Jim Morrison was inspired by the title of one of Aldous Huxley's books, "The Doors of Perception". The title itself was derived from a line in William Blake's "The Marriage of Heaven and Hell" poem: "If the doors of perception were cleansed, everything would appear to man as it is, infinite".

S&P Global Ratings doesn't profess to know the infinite, or for that matter, what will happen in the long term. But we have views on the current and medium-term trends. Over the next several weeks, in a series of articles titled "Foresight Is 2020," we will provide our views on some major themes in the power sector, such as the latest developments in battery economics and technologies, and in contracts in renewable power that include merchant tails. This article will focus on developments in, and key credit drivers for, offshore wind in the U.S.

Latest Developments In The U.S. Offshore Wind Industry

Renewable energy standards (RPS) or carbon reduction goals are driving market activity in states--such as California and Hawaii--without offshore wind procurement targets. However, this article focuses on developments in the Northeast, because most queries that we receive from investors are largely limited to this region.

Despite only one operating offshore wind farm, Block Island (30 megawatt [MW] in output), the U.S. currently has an aggregate pipeline of more than 26 GW in offshore wind capacity in federal lease areas. Out of this pipeline, developers expect 14 offshore wind projects totaling 9.1 GW to be operational by 2026 (see table 1). All market consultants with whom we spoke agree that the capacity could exceed 12 GW by 2030, but regulatory uncertainty will influence the speed of build-outs. (Vineyard Wind's permitting has been delayed at least until March 2021).

Table 1

Pipeline Of U.S. Offshore Wind Projects
Project name Sponsors Size (MW) COD Offtake mechanism Pricing ($/MWh) Counterparties Term (years) Location and turbines Remarks
Massachusetts
Vineyard Wind 1 (Martha's Vineyard project) Avangrid/Coppenhagen Infrastructure Partners 804 2022 PPA $74/MWh for 400 MW (2022) then $65 for the next 400 MW (2023) with a 2.5% escalation per year Eversource, Unitil, National Grid 20 South of Massachusetts’ Martha’s Vineyard island. MHI Vestas will supply 84 of its V164-9.5MW turbines. Nominal levelized at $84.23/MWh over contract period. It may still qualify for the 21% ITC as permitting delays can possibly be recognised by tax authorities as a valid reason to maintain pre-qualified tax-credit levels.
Mayflower Shell Oil and EDP Renewables 804 2025 PPA Being negotiated but likely below levelized cap of $84.3/MWh Eversource, Unitel, NSTAR 20 26 nautical miles south of Martha’s Vineyard and 20 nautical miles south of Nantucket. The original enabling legislation mandated that for each round of offshore wind procurement, the cost must come in lower than for previous procurements. Given the expiration of the ITC and the low price in Vineyard Wind’s winning bid in 2018, it was determined that future bids could be for higher amounts, provided that the increased cost was accounted for and justified. Bladt and Semco to supply a 1.2GW offshore substation.
Rhode Island
Block Island Deepwater (Orsted) 30 2016 PPA $244/MWh with a 2.5% escalation pace National Grid 20 3.5 miles from Block Island in the Atlantic. Five Alstom Haliade 150-6-MW turbines. Contributing to the project’s support in that it connects Block Island to the New England grid, allowing it to avoid high cost diesel generation that the island otherwise relied upon.
Revolution Wind Ørsted and Eversource 400 2023 PPA $98.4/MWh National Grid 20 Deepwater ONE North zone 704 MW between the Connecticut and Rhode Island PPAs.
Connecticut
Revolution Wind 1 & 2 Ørsted and Eversourse 304 2023 PPA $94.0/MWh Eversource and United Illuminating 20 Deepwater ONE North zone. Siemens Gamesa won a conditional supply contract for 8MW SG 8.0-167 turbines. Eversource and United Illuminating agreed to buy 200MW at $94/MWh and an additional 100MW with pricing set to be made public.
Park City Wind Avangrid/Coppenhagen Infrastructure Partners 804 2025 PPA Currently being negotiated Eversource and United Illuminating 20 23 miles off the coast of Massachusetts
New Jersey
Ocean Wind Ørsted and PSEG 1100 2024 Offshore Wind Renewable Energy Credits (ORECs) $98.10 OREC price escalates at 2% through 2045. Equates to a nominal levelized price of $116.82/MWh. However, the levelized net OREC cost - which represents the actual ratepayer OREC costs after refunds of capacity and certain other revenues - is estimated at $46.46/MWh over the contract life. PSEG 20 15 miles off Atlanctic City's coastline. 90 GE Haliade-X turbines. The NJ BPU’s OREC funding mechanism is largely based on the procurement of a bundled energy, environmental attribute and capacity product. The use of an OREC adds complexity with respect to the administration of the ORECs and risk to developers (e.g. variances between actual and forecast output) and in opinion could be more simply administered with stronger performance incentives with a PPA that procured energy and environmental attributes. The project will be developed in 3 tranches of 368 MW each in partnership with PSEG.
New York
Empire Wind Equinor (formerly Statoil) 816 2024 OREC $83.36/MWh with an OREC offset of $25.14/MWh. Payments rise and fall based on a composite average of energy and caapacity prices. Nyserda will buy ORECs from Equinor and resell them to load-serving entities to meet their obligations under the state's offshore wind standard Nyserda 25 The $3 billion project will employ 80 turbines in a triangular segment of the Hudson North zone facing Long Island. Strike prices are assessed by: (1) an index OREC price and; (2) a fixed OREC price. The index OREC price will vary monthly based on the value of index OREC strike price specified minus the monthly reference energy price and the monthly reference capacity price. The fixed OREC price is based on the fixed price specified by the proposer. The index OREC price is a contract for difference that considers relevant energy and capacity prices, thereby providing a market price hedge. The index OREC price is given a weight of 0.9 and the fixed OREC price a weight of 0.1 to establish the weighted strike price.
Sunrise Wind Bay State Wind, LLC (Orsted and Eversource) 880 2024 OREC Nyserda 25 Developed adjacent to the Revolution and South Fork projects in the Deepwater ONE North zone, about 48km (30 miles) east of Montauk Point, Long Island. Siemens 8MW SG 8.0-167 turbines.
South Fork Ørsted and Eversource 90 2022** PPA Undisclosed Long Island Power Authority 20 Deepwater ONE North zone off the coasts of Rhode Island and Massachusetts. Siemens Gamesa a conditional contract to supply 8MW SG 8.0-167 turbines.
Maryland
US Wind Renexia Spa 248 2020 OREC Maryland awarded ORECs for 20 years at $131.94/MWh (one OREC for each MWh delivered to the grid) 20 32 turbines; 17 miles off Ocean City Each year, 913, 945 ORECs will be sold at a levelized cost of $131.94/MWh
Skipjack Ørsted 120 2023** OREC $131.94/MWh 20 Off the coast of Delaware. Ten 12MW GE Hallide -X turbines. Each year, 455, 482 ORECs will be sold at a levelized price of $131.94/MWh.
Virginia
Coastal VA offshore wind Utility owned 12 2022 PPA $780/MWh Vepco
Dominion Utility owned 2600 2025-2026 Undisclosed; indications of $78/MWh Vepco
*Included only projects past permitting phase. These projects exclude others like Icebreaker (Ohio) and Aqua Ventas (Maine) , which are relatively small and were orginally funded under the DOE advanced technology demonstartion project program **Still require some federal permits.

Projects progressing through the offtake and permitting approval process continue to be primarily located in the Northeast, where state-level procurement drives the market and project development. Six states have targeted nearly 6.3 GW of offshore wind capacity through state-issued solicitations. Multiple projects also made significant progress with electricity offtake agreements and environmental permitting at both the state and federal level.

In 2019, state-backed targets and renewable mandates for clean energy continued to build momentum with about 26 GW of offshore wind procurement targets established to date. (To be clear, the pipeline of offshore wind projects and state-backed mandates for such power source generation are separate from each other, but are coincidentally 26 GW each). This capacity, compared with just 8 GW in mid-2018 (see chart 1), will account for about 30% of the 86 GW of total U.S. offshore wind capacity, according to the Department of Energy' (DOE) forecast through 2050.

We expect Maryland and North Carolina to be the next states where we could see increasing activity, particularly as a frontrunner developer in these states hasn't been established.

image

The industry got yet another fillip in September 2019 following Virginia governor's executive order calling for 2.5 GW in offshore wind capacity in the state by 2026. Shortly after, Dominion Energy, Inc. announced plans to build and own a 2.6 GW offshore wind farm, the largest project announced in the U.S. to date. The latter will extend the offshore footprint further south along the eastern coastal states, whereas North Carolina, South Carolina, and Georgia have yet to announce mandates for such power generation. There's also a rising interest in developing projects along the Pacific Coast and the Great Lakes region. The West Coast, especially northern California and southern Oregon, has good wind resource but will likely require floating installations because water depths are deeper.

On the federal level, the Department of Interior's Bureau of Ocean Energy Management (BOEM) has issued 15 active commercial wind energy leases so far. In 2020, we expect additional solicitations, because Massachusetts, New Jersey, and North Carolina possess substantial offshore wind resources. BOEM is currently in the planning stages for areas off the coasts of California, Hawaii, New York, and South Carolina, and the agency expects to hold lease auctions for new lease areas off the coasts of California and New York later this year.

U.S. Offshore Wind Is Currently Uneconomical

Our estimate for the LCOE for U.S. offshore wind, excluding an investment tax credit (ITC), is about $85/MWh. A 30% ITC lowers our estimates to about $65/MWh (see table 2). Our major assumptions for overnight capital costs and capacity factors are $3,600 per kilowatt (kW) and 44%, respectively, for the initial projects. Nevertheless, some projects in Europe along with those for competing technologies, have lower LCOEs.

The table below shows in more detail our assumptions, which are influenced by O&M costs, debt equity ratios, financing costs, depreciation methods, etc. For example, we may be conservative on capacity factors, but somewhat aggressive on O&M cost assumptions.

image

Skeptics point to offshore wind projects' current economics and the infrastructure needs, and costs, while proponents allude to a rapid pace of innovations in the industry. We acknowledge that our LCOE outcomes could vary widely because of a number of variables. But we believe our analysis provides relevant guidance on what could drive both the opportunity and the risks for offshore wind generation. In discussions with industry experts and acknowledging the potential for significantly lower costs, we're cautiously optimistic about prospects for offshore wind energy output. However, given these estimates, the onus is on the industry to convince us of offshore wind's potential from a credit perspective.

For transparency, we have presented our detailed assumptions in the appendix. We believe our sensitivities capture the wide range of possibilities, based on which we make the following observations:

  • Without ITC, the current LCOE levels for offshore wind are substantially higher than those for alternative energy sources, such as natural gas peakers and onshore wind at $68/MWh and $40/MWh, respectively.
  • Unlike renewable energy sources such as onshore wind or solar PV, competitiveness of which against natural gas- and coal-fired generation has risen on the LCOE basis, offshore wind currently doesn't fare well; a point which NextEra Energy Inc. underscores in its criticism, which we will get to later in the article.
  • O&M costs vary widely. In our model, a 30% increase in O&M costs to $125/kW per year increases the LCOE requirement by $5/MWh.
  • Yet, the levelized value of merchant payments from wholesale power--say about $40/MWh, capacity at $5/MWh, and renewable energy credits at $25/MWh--could be similar to the contract price for the Vineyard Wind project, implying that states wouldn't be paying a significant premium for meeting renewable targets in 2023-2025.
  • LCOEs for offshore wind facilities have shown two broad trends: a secular decline in prices, but countered by the persistence of price disparity among various markets. The price differentiation is somewhat structural, given that the scope of projects varies across markets; i.e. generation only versus generation and transmission.
  • The ITC and technological innovations substantially contribute in driving down offshore wind LCOE towards those of conventional technologies. For instance, we believe a 10% increase in capacity factors, or the reintroduction of a 30% ITC, drops LCOE by $20/MWh, while other factors remain unchanged.

But Investors And Lenders Are Taking Much Greater Interest

At a recent industry forum, a banker noted that there were more than 50 financing entities that have a 'real interest' in lending to offshore wind projects in the U.S. Given that most market participants agree that offshore wind has yet to post a competitive challenge to other energy sources, that level of interest is counterintuitive. Nevertheless, we believe investors' interest stems from the following factors:

  • The potential for a dramatic decline in costs once the industry scales up, as seen in Europe's experience.
  • Some risk-offsetting features compared with onshore wind generation.
  • Resource characteristics that mitigate other types of risks.

We will discuss the potential for lower LCOE later in the article, but we underscore the risk-mitigation potential of offshore wind.

Risk comparison among renewable power sources

Revenue contracts.  Risks for offshore wind farms are different from those that onshore counterparts face. Due to several years of experience under the belt--in terms of construction, turbine performance, O&M cost predictability, and track record of power generation--risks for the onshore wind asset class has substantially subsided. Consequently, sponsors are now introducing merchant tails in onshore wind financings in the U.S. and a similar trend is taking shape in Europe's offshore wind industry. In contrast, we expect offshore wind output in the U.S. to be largely contracted, but such facilities will bear construction and O&M risks. Offshore wind farms also grapple with intricacies of tax-credit qualifications and turbine risks, although the latter are largely borne by turbine manufacturers.

Resource characteristics.  Not only onshore wind generates lesser volume of energy, location of such facilities is often far from major load centers. In contrast, offshore resource is closer to major load centers and higher-priced wholesale power markets. However, we believe production forecasts could be affected by 'blockage' and 'wake' effects (see notes at the end of the article). These factors could affect the estimates of third-party data providers during forecasting for resource levels.

Expected capacity factors.  As a rule of thumb, the industry expects offshore wind capacity factors of 40%-50%, about 10% higher than those of onshore wind farms. At these levels, offshore wind matches the capacity factors of gas- or coal-fired generation in many regions. Moreover, capacity factors for offshore wind farms are the highest in the evening (typically 45%-50%) and coincide with peak power prices during that period. Offshore wind capacity factors are also highest in the winter months (50%-55%)than in the summer (25%-30%). Importantly, while offshore wind's availability is still variable, its hourly variability is markedly lower than that of solar PV. It typically fluctuates at about 20% from hour to hour, compared with 40% for solar PV.

These metrics point to offshore wind's potentially higher efficiency than that of onshore wind and PV solar generation. Yet, the track record of an offshore wind asset, particularly in seabed conditions is currently unknown: wind farms in Europe have been operational only for 10 years.

States Are Mandating Offshore Targets

Although offshore wind has a long way to go to challenge other energy sources, interest has increased dramatically at the U.S. state level in recent years, largely because of the following factors:

  • Meeting RPS goals and shifting away from natural gas- or coal-based power;
  • Expectations of a substantial decline in costs due to innovations; and
  • The lure of boosting local economic development and job creation.
Attaining RPS goals

Reliance on natural gas generation among states with offshore wind output targets is higher than the national average of 35%. For instance, such power generation accounts for about 50% of New Jersey and Massachusetts' total output. While gas-fired generation in New York is about 35% because New York City relies on the Indian Point nuclear power plant for 15%-38% of its needs, while the state plans to shutter this plant in 2020 and 2021, and its output has been already replaced by two 1,000 MW CCGTs.

According to table 5 in the appendix, our calculations show that the Northeast could reduce its natural gas usage by more than 2.5 billion cubic feet per day if the currently announced offshore wind mandates of 26 GW are implemented. We made the simplifying assumption that the gas-fired plants with an average heat rate of 8,500 British thermal units per kilowatt hour operating at a 50% capacity factor, are displaced at the same rate as an offshore wind farm (with the same capacity factor) is brought online.

In addition to helping states in attaining RPS targets, offshore wind generation helps wean these states away from natural gas, enabling them to reach their regional greenhouse gas initiative (RGGI) targets.

The potential for falling costs due to innovations

According to the International Energy Agency (IEA), global average overnight capital costs (including transmission) are projected to decline to $2,500/kW by 2030 from $4,350/kW in 2018. This is based on assumptions that capital costs fall 15% each time the global capacity doubles. The global offshore wind market grew nearly 30% per year between 2010 and 2018. WindEurope, an association that promotes the use of wind power, estimates that capital costs for offshore wind farms (excluding transmission) for 2018 on the continent were about $2,870/kW, a 45% reduction since 2015.

The industry expects that roughly half of the decline in future costs will come from efficiency gains by using larger turbines. This will reduce the number of turbines to be installed and serviced, lowering the balance-of-plant costs, and raising the energy per unit of area. Manufacturers have reportedly been able to increase the turbine structure without lifting its unit cost. The average offshore turbine size rose to 5.5 GW in 2018 from 3.0 GW in 2010. In 2018, the largest installed turbine was MHI-Vestas 8.8 MW. Moreover, the trend of upscaling existing turbine platforms was disrupted by plans to roll out prototypes with larger rotor diameters (such as GE's 12 MW Haliade-X and Siemen's SG 10.0-193 DD) in 2021-2022. The industry is targeting even larger, 15-20 MW, turbines by 2030. Similarly, as the power capacity of turbines continues to rise, wind developers and operators are increasingly shifting to the 66–kV array cable technology from the conventional 33-kV systems, leading to lower electrical infrastructure costs. Table 6 in the appendix contains our assumptions, showing how larger rotor diameters improve turbine production and reduce costs.

The potential to bolster local economic development

The plot thickened after NextEra, a large electric utility and renewable energy proponent, came out strongly against offshore wind last year. However, at about the same time, Dominion Energy announced an $8 billion investment in offshore wind farms. We actually think both positions have merit, despite the apparent contrarian positions.

NextEra based its argument on its assessment of the potential for higher infrastructure costs, cost overruns, and timing delays. The company's views are premised on its success in the renewable space and the tried-and-tested economics of its onshore wind and solar PV businesses. The company believes that the U.S. has vast and still untapped onshore renewable resources. It also stated that the U.S. faces lower obstacles in expanding the onshore wind capacity than countries across the pond. Separately, yet related, we note that Florida has a lesser offshore wind resource and a coastline not as conducive for such a build (current offshore wind turbines are designed using IEC 61400-03 standards, which define a three-second maximum gust condition of 156 miles per hour).

On the other hand, once state officials decide that offshore wind is in the 'public interest', it's logical for the incumbent utilities to consider this source in their energy mix, given a likelihood of rate-based treatment. Dominion Energy's decision came soon after Virginia's executive order ushering in an offshore mandate. Given the European offshore wind farms' achievement of dramatic cost cuts underscores the U.S. players' willingness to jump on the bandwagon.

But there are other factors at play. States are announcing offshore wind renewable targets because at stake is an opportunity to also jumpstart a supply chain, estimated at $70 billion based on nearly 20 GW of offshore facilities that we expect to be constructed over the decade to meet state policy requirements. Indeed, it's a race; build them and they will come.

Many states on the East Coast already have a fairly robust maritime economy. For instance, Virginia boasts shipyards, large naval facilities (submarine manufacturing, etc.), Coast Guard, the fishing industry infrastructure, and coastal residential communities. Turbine manufacturers may consider such factors as sufficient to establish a supply chain on the Eastern Seaboard. These include new ports and expansions of existing ones, harbor redevelopments, and manufacturing facilities.

Incentives for local development are already incorporated in several auction outcomes. For example, in its 2019 auction, Massachusetts chose the bid package that had the lowest cost, while New Jersey chose the one that offered the highest local content. Massachusetts is somewhat unique among states procuring offshore wind projects, given that its bid evaluation process is driven almost entirely by costs. However, pressure is mounting on Massachusetts to consider the effects on local economic development. The ability to justify a higher cost and the drive to increase local content has prompted some wind developers to offer a range of options from strictly low-cost offerings to those

Table 3

Examples Of Local Incentives And Local Content
Project name Local incentives/development
Mayflower $3.7 billion of rate reduction and 10, 680 jobs over the project. $1.2 billion of spending in economically stressed regions. 75% of O&M jobs will be local.
Revolution Wind 1 and 2 A $93 million infrastructure upgrade. At least $15 million investment in the State Pier to allow substantial aspects of the project to be constructed in New London. Significant portions of construction and/or assembly will occur in New London, including foundation components and the offshore substation. Contracting with a Connecticut-based boat builder to construct one of the project’s crew transfer vessels in Connecticut.
Park City Wind $890 million in direct economic development (local supply chain and bridgeport harbor), and includes redevelopment of an 18.3 acre waterfront industrial property.
Ocean Wind The winning bid expects to generate $1.17 billion in economic benefits, in addition to creating about 15,000 jobs over the project life. New Jersey’s BPU said Ørsted won partly on the basis of having the most detailed plans for economic development in the state, including the strongest guarantees around local content and manufacturing. Among other commitments, Ørsted plans to open an operations and maintenance base for the project in Atlantic City.
Source: S&P Global Ratings.

Given that certainty in state policy and commitment towards offshore wind generation is a pre-requisite, we believe development of such projects is likely in those states that pursue RPS targets aggressively, and have a relatively predictable political environment because offshore wind farms require meaningful time spanning from permitting to the completion of construction.

What Are Our Expectations?

We expect M&A activity to ramp up, both at a company and asset level. Despite losing to Vineyard Wind in Massachusetts' first offshore wind solicitation, Ørsted acquired a developer, Deepwater Wind, for $510 million. The purchase gave the company the largest footprint in the U.S. market, with offtake deals in New York, Connecticut, Rhode Island, New Jersey, and Maryland.

Developers are forging partnerships with incumbent utilities to ease the way in winning offtake contracts. With its partnerships with Public Service Enterprise Group (PSEG; Ocean Wind) and Eversource Energy (Revolution Wind and Sunrise Wind), we view Ørsted as a clear frontrunner at this stage. We expect other major developers--such as Equinor ASA, a subsidiary of Norway's Statoil ASA, and a joint venture between Shell Energy North America (US) LP and EDP Renewables--to continue exploring partnerships. Consolidated Edison, Inc. and Dominion Energy have yet to commit to a partner for a 2.6 GW project. Ørsted is developing a demonstration project off Virginia's coast in partnership with Dominion, but the latter has yet to make a decision.

Finally, Equinor recently won a New York solicitation, while Shell New Energies (a subsidiary of Royal Dutch Shell plc) is operating in Massachusetts through Mayflower Wind. It's no coincidence that a number of oil majors--Royal Dutch Shell, Statoil, and Eni SpA--are also offshore wind developers. These companies have many reasons to move into the industry. They've spent decades building oil projects offshore, and that business is winding down in areas where older fields have been depleting. Returns from wind farms are predictable and underpinned by long-term contracts. And oil giants want to get a piece of the clean-energy business amid forecasts that renewable energy will eat into their market shares.

The IEA estimates that about 40% of the full lifetime costs of an offshore wind project, including construction and maintenance, has synergies with the oil and gas sector. Given that offshore energy operations share technologies with offshore wind facilities, oil and gas companies started investing in offshore wind projects many years ago.

Risks Of Venturing Out Into The Deep Waters

Europe had little choice but to take the sea route due to lack of available land for further onshore wind power facilities. In the U.S., wind developers will also grapple with risks of constructing offshore platforms, because building the transmission infrastructure will be their responsibility (see sidebar 1). In discussions with industry experts, it became apparent that the major concern over U.S. offshore wind generation doesn't pertain to resource risk, turbine performance, or even construction. Instead, unplanned costs of upgrading onshore transmission, placement of projects in independent system operator (ISO) queues to interconnect on time, and the areas to tie in offshore cables became the larger focus. Integrating 26 GW of the proposed offshore wind output on the East Coast will almost certainly require the development of networked offshore grids and approximately 3,000 miles of offshore transmission lines.

We classify offshore risks in the following matter:

  • Ability to achieve capacity factors similar to European levels (energy production);
  • Hardening of grid and existing infrastructure; and
  • Logistics barriers: the Jones Act, import of components, and other O&M issues.
Ability to achieve capacity factors

Potential sites in the U.S. don't have as detailed data about geological, oceanographic, and meteorological conditions as European projects, which increases the initial development risks of wind farms, and consequently, the costs to finance them. With the development of projects and collection and verification of data, the uncertainty associated with these variables would diminish. From a credit perspective, there's no way to quantify this, and our analysis would likely incorporate a lower capacity factor (for example, 44%, compared with higher levels in Europe).

Hardening of onshore grid infrastructure and establishing offshore transmission

For transmission operators, position in the queue ultimately dictates what upgrade costs are necessary for onshore grid. In New York, for instance, the wind resource is 15-30 miles offshore, and access to it is limited by shipping lanes emanating from New York City. Given congestions that are typical in New York, there are limited interconnection opportunities with the onshore grid.

In New England, onshore interconnection are even further from the offshore sites than in New York. As a result, interconnections by using the existing transmission infrastructure at retired coal-fired power plants (such as Brayton Point) are vital and will require transmission build-out for grid reliability purposes. Similarly, at New Jersey's southern end, aside from the Oyster Creek nuclear power plant, the onshore grid is fairly weak, likely requiring significant reinforcements at local landing points, or building offshore connections to more robust--but more distant--landing points in the northern part of the state.

Logistics issues

Depth and distance.  Ideally, offshore wind farms should be located within a 'goldilocks' distance from the shore: not too close because of the potential of public backlash, as seen in the abandonment of the Cape Wind project, but not too far, because of greater costs and complexity. We believe the ideal distance is about 25 miles from the shore. This is also the distance at which the HVAC or HVDC decision becomes crucial. (Besides, 26 miles is equivalent to 42 kilometers, and 42 is the answer to the riddle of the universe).

We should mention that in assessing a project's cost and complexity, it's more relevant to consider the distance to critical infrastructure than that to the shore. As more projects are permitted and constructed, developers may run into more difficulty finding suitable grid connection points, requiring longer export cables. Nevertheless, the distance between the wind farm and service port will be a weighty cost factor, because access to turbines, as well as construction and O&M costs are directly related.

We note that U.S. projects will likely be built at a greater depth (even on the Eastern Seaboard) than their European counterparts. Northern Europe's sea landscape is characterized by the shallow bathymetry of the North Sea, allowing wind farms to be located far from the shore while still using fixed-bottom foundations.

Availability of barges for installations.  We highlight that the availability of U.S.-made barges, which can transport offshore wind equipment to the foundation, is also in limited supply. Before a supply chain on the Eastern Coast is built out and/or a U.S.-made installation vessels are manufactured in sufficient numbers, we believe more capex and construction time must be budgeted into plans.

While multiple marine engineering companies (such as GustoMSC B.V., Zentech Inc., and A.K. Suda Inc.) have drafted designs and conducted cost studies for U.S.-flagged installation vessels, very few offshore installers announced construction of a new vessel through 2018. In fact, only as recently as December 2019, the first U.S.-based offshore wind service operations vessel (SOV) to be compatible with the Jones Act was approved by the American Bureau of Shipping, a maritime classification body. The SOV, which Canada-headquartered Vard Marine developed, is designed to provide personnel accommodation, transfer technicians to offshore turbines, as well as storing spare parts and tools for U.S. offshore wind farms. According to the latest DOE report on offshore wind, the only known vessel development in 2018–2019 was Ørsted entering into partnership with WindServe Marine to construct two crew transfer vessels--one in North Carolina and the other in Rhode Island--for use at the Coastal Virginia Offshore Wind and Revolution Wind projects.

Imported components.  Not surprisingly, there are significant gaps in the U.S. offshore wind supply chain that prevent the realization of cost savings comparable to those in Europe. Currently, the U.S. supply chain is not well inventoried, and lacks necessary workforce, port facilities, etc. Almost all of the offshore wind components, including rotors and turbines, slated for the U.S. projects are currently manufactured in Europe. The supply chain expansion in the U.S. would further reduce costs, as proximity decreases transportation costs and fosters better communication between the supply chain members. This clustering strategy also allows for more robust project management and top-to-bottom collaboration on projects. This ties back to our comment on the speed of state mandates. States are announcing their commitments to offshore wind with the aim of attracting the supply chain members to set up shop near the sites.

What Does All This Mean For U.S. Offshore LCOEs?

To get a better insight of the potential for reducing costs, along with risks, we took a stab at comparing U.S. and European LCOEs. To do this, we incorporated our estimates for U.S. and European costs in our LCOE model. We bucketed the variables into one of the risks noted above. This helped us identify what factors need to improve most in order for U.S. costs to decline to European levels. So, for instance, enhancing existing infrastructure and grid connections would diminish the difference in our capital costs estimates, while costs associated with the Jones Act are captured in the differences in O&M costs. The table and chart below summarize our assumptions and results.

Information in table 4 is illustrative but shows where cost reductions would have to be achieved to reach European price levels. Note that this analysis doesn't assume any ITC benefits.

Table 4

Assumptions In Our LCOE Model
(2024-2025 COD)
U.S. East Coast Latest German auction Remarks
Capacity factors (%) 44 50 Global offshore wind capacity factor averages have improved to 43% from 38% in 2018 and are likley to be higher. We have chosen 44% to account for the fact that a proven technology is being used at locations where resource data is not as robust as in Europe.
Overnight capital cost ($/kW) 3600 2850 Recall that German costs are ex-transmission. We capture the difference in grid connection and hardening of existing infrastructure costs here. While some projects would beat this estimate, we think that the 2022 estimates of $3,000/KW, assumed by a major project, are aggressive.
O&M costs ($/kW per year) 95 75 We capture logistics issues through this difference. Major items here would be costs associated with the Jones Act as well as import of components (currency differences and transportation costs). We think this assumption could be aggressive. U.S. projects would need to demonstrate ability to come in under this level.
Cost of equity (%) 12 12 European returns are lowering . We've assumed 12% is a return developers should be able to earn in Europe even as competition accelerates. While the U.S. is riskier, we've assumed no difference as developers are more interested in scaling.
Cost of debt (%) 5.5 3.5 Debt rates for global offshore wind financing remain at historically low levels, ranging between 3% and 4% for 15-year debt terms.
Risk premium (%) 8 Consultation with industry experts suggests that early commercial-scale U.S. projects might expect higher contingency levels relative to the established European offshore wind markets.
Source: S&P Global Ratings.

As we mentioned earlier, in many countries, including Germany and France, wind developers are responsible solely for completing the wind farms. However, in the U.K, Japan, South Korea, and the U.S., developers are also responsible for building out transmission. Based on our assessment, about 50% of the cost difference stems from the higher infrastructure and grid connections costs, which we believe will be tough to address.

Wind developers in the U.S. could learn from the overseas experience. The industry has to avoid repeating the mistakes made by the oil majors during the LNG infrastructure construction in Australia, which experienced significant cost overruns due to duplication of infrastructure. This highlights the need to disperse the costs in a collaborative manner among developers and constructing offshore- and onshore-shared services wherever possible.

A step in the right direction is the partnership between Anbaric and the Ontario Teachers' Pension Plan, which filed an application with the BOEM in November 2019 to develop an open-access offshore transmission system that will connect up to 16 GW of offshore wind energy to southern New England states. The Southern New England OceanGrid project would be established on the outer continental shelf in order to link the existing wind lease areas in Massachusetts, Rhode Island, and Connecticut through a common system. Similarly, the New York/New Jersey OceanGrid 1,200 MW project proposes to minimize the number of cable routes through the connection of multiple wind farms to HVDC cables that run to the shore.

Chart 2

image

Our conclusions are consistent with those of the IEA's March 2019 "Special Report Offshore Wind Outlook 2040" regarding the differences between the European and U.S. LCOEs. The IEA notes that the U.S. would require supportive policies like the ITC--even as costs decline--to bridge the gap with Europe. The IEA captures the lower variability of the offshore wind resource in its value-adjusted LCOE.

Wind Of Change

The offshore industry started just 30 years ago. Elkraft, one of the predecessors of DONG Energy (now Ørsted), began considering offshore turbines in the late 1980s. Eventually, the Vindeby offshore wind farm, the first in the world, started out with a survey of the waters around the Danish island of Lolland in 1989. Construction was commissioned off the coast of the town of Vindeby, and the project was commissioned in 1991. This was also a momentous time in Europe with the promulgation of large-scale socioeconomic changes in the former USSR, and the fall of the Berlin Wall.

That brings us a full circle back to our musical references. In 1990, to commemorate the changes sweeping across Europe, Scorpions, the German rock band, released a single called 'Wind of Change'. The song topped the charts in Germany and across Europe and peaked at number 4 in the U.S. and number 2 in the U.K. The power ballad may as well have been written for the offshore wind industry: "The future's in the air, can feel it everywhere, blowing with the wind of change".

Offshore wind is indeed changing the European power landscape. It remains to be seen if the industry brings in sweeping changes to the power industry in the U.S.

Related Research

  • The Energy Transition: Is Offshore Wind Done Or Going For Other Bids?, Feb. 18, 2020
  • Offshore Wind: A Changing Sea Of Risk, Oct. 3, 2017
  • Offshore Wind Projects Take Off As Technology Improves And Costs Fall, June 2, 2017
  • With Offshore Wind Projects Set To Take Flight, What Factors Will Move Ratings?, Feb. 12, 2016

Appendix

Our Base-Case LCOE Assumptions (In Table 2 we have provided sensitivities)

Capacity factors: 44%

Initially, 44% in the U.S. to take account of the 'blockage' and 'wake' effects. Ørsted has noted that these can become significant. We will assume load factors at this level unless proven otherwise. We note that the industry assumes 48%, given that Block Island registered such a level. Ørsted has recently come to the same conclusion. We acknowledge that based on improving technologies, the industry has the potential to surpass these estimates.

Overnight capital costs: $3,600/KW

A recent National Renewable Energy Laboratory paper estimates overnight capital costs at about $3,800/kW, but notes that the range could be from $2,500/kW to $5,700/kW. Separately, DOE notes that global capital costs ranged between $2,500/kW and $6,500/kW in 2018. We view $3,600/KW of capital costs for the initial projects despite the sponsors' lower estimates.

Several factors may explain the variation in capital costs:

  • Varying spatial conditions (e.g., water depth, distance to the port, point of interconnection, and wave height of sites that affect technical requirements of installing and operating a wind farm);
  • Project size (typically 400 MW and higher have statistically lower capital costs);
  • Various levels of supply chain shortages (e.g., components, vessels, and skilled labor); and
  • Risk premium and bidding behavior (pricing strategies from equipment suppliers and installation contractors).
O&M costs: $95/kW per year or about $19/MWh

O&M cover all costs incurred after COD--but before decommissioning--that are required to operate the wind farm and maintain turbine availability to generate power. These expenditures are generally thought to contribute between 20% and 30% to life cycle costs, depending on site characteristics. The strongest drivers are distance from the O&M port, accessibility limits related to local meteorological conditions (e.g., wave height), and turbine rating (fewer, larger turbines mean lower O&M costs per MW). The estimate we used is 23%-25% of the overall lifetime costs. These are the toughest to estimate because they wary widely for existing projects---ranging from $65/kW per year to nearly $200/kW per year. We believe we may be a bit aggressive in our assumptions, and O&M costs could be higher for the initial projects.

Cost of debt: 5.5%

Debt interest rates for global offshore wind remain at historically low levels, ranging from 3% to 4% for 15-year debt terms. Initial projects will likely tap loans from banks because the latter are more flexible during construction period. This is our institutional market estimate for a 15-year financing. (In the U.S., lending is usually 7-10 years.)

Cost of equity: 12%

Revenue contracts have no merchant risk but permitting risks are significant. In the U.S., a federal, state, and local permit to construct and operate a wind power plant is not included in a lease award. This might introduce additional risks such as legal action, permitting delays, and stranded assets, compared with those of acquiring a fully permitted lease area.

Debt/Equity: 65%/35%

We assumed no ITC in our LCOE calculations. In the scenario where we used 30% ITC benefits, debt/equity was rebalanced to 50%/50%.

Asset life: 25 years

The longest offtake contracts (New York) are for this term. Most are 20 years.

Depreciation: we used MACRS

Projects with the COD prior to 2022 can use 100% bonus depreciation with a phase down. We didn't, to be conservative.

Risk premium: 8%

Installation and operation contingencies. Consultations with industry experts suggest that early commercial-scale U.S. projects might expect higher contingency levels relative to the established European offshore wind markets. These serve to account for lesser experience in the U.S. offshore wind power plant installation and operation with the risk of incurring delays and interruptions in the supply chain, marine logistics, and permitting processes.

Investment tax credits

We didn't consider them, but they would be an upside. Two bills in Senate—the Markey-Whitehead six-year extension of a 30% credit, and Carper-Collins extension of the 30% credit through 2027, or 3 GW installed, whichever comes first. An additional consideration affecting project economics is whether offshore export cables qualify for ITC inclusion. The issue is whether the cable is considered a part of the generating equipment of an offshore wind farm. Vineyard Wind may likely qualify for the 21% ITC, given that permitting delays can possibly be recognized by tax authorities as a valid reason to maintain pre-qualified tax-credit levels.

Table 5

Regional Natural Gas Displacement
Amount of Gas displaced (Bcf/d)
CCGT (MW) 1,000 a
Capacity factor (%) 50% b
Hours in a year (Hr) 8,760 c
Average heat rate of displaced Units (mmBTU/MWh) 8.5 d
Energy produced (MWh) 4,380,000 e=a*b*c
Gas needs (mmBTU) 37,230,000 f=e*d
Days in a year 365 g
Natural gas displaced (BCf/d) 0.102 h=f/(g*1000000)
Displacement of 26 GW (bcf/d) 2.65 h*26
1 mmBTU= 1 MCf 1=BCf= 1,000,000 Mcf. Source; S&P Global Ratings.

Table 6

Turbine Blade Efficiencies To Lead To Cost Reductions
Remarks
Diameter of the rotor blade 90 220
Radius (mtr) 45 110 a
Area of the circle swept (m2) 6,359 37,994 b=∏ * a2
Speed of air (m/s) 10 10 c 20 miles/hr; converted from mtr/sec to miles/hr
density of air (kg/m3) 1 1 d
Mass of air in kg/sec 63,585 379,940 e=b*c
Kinetic Energy (joules/sec) 3,179,250 18,997,000 0.5 *m*v2 kinetic energy of the wind
Kinetic Energy (in Watts) 3.2 19.0 MW joules/sec= Watts
Efficiency of a turbine blade 45% 45% See note on maximum efficiency of 59%
Power (MW) 1.43 8.55 MW Scaled up 6x by only doubling the rotor diameter
Source: S&P Global Ratings.

Table 7

Current State Offshore Wind Mandates
State Nearest RPS goal RPS year Offshore capacity commitment (MW) Statutory authority Year enacted
NY 70% 2030 2,400 Case 18-E-0071 2017
6,600 Climate Leadership And Community Protection Act 2019
NJ 50% 2030 3,500 Executive Order 8; Assembly Bill 3723 2018
3,500 Executive Order 92 2019
MA 35% 2030 1,600 House Bill 4568 to promote energy diversity 2016
1,600 House Bill 4857 to advance clean energy 2018
CT 31% 2030 300* House Bill 7036 2017
2,000 House Bill 7156 2019
VA 2,500 Executive Order 43 2019
MD 50% 2030 1,200 Senate Bill 516 set targets 2019
RI 38% 2035 1,100 No specific statuatory Bill
Notes: RPS goals are staged over time. Only nearest goals are included. *100 MW came from technology-neutral auctions

Notes

The 'blockage' effect arises from the wind slowing down as it approaches the wind turbines. There's an individual blockage effect for every turbine position and a global effect for the entire wind farm, which is larger than the sum of the individual effects.

The 'wake' effect is the slowing in wind speed, occurring in the individual wind farm and between neighboring ones. The phenomenon is caused by a turbine. But as the wind flow continues, the wake effect diminishes and the wind speed recovers.

In 1919, a German physicist, Albert Betz calculated that the most efficiency that you extract from a wind turbine is 59%. To explain this, imagine a turbine that could extract 100% of the kinetic energy from the wind flow. No kinetic energy left in the wind means no velocity left in the wind. If the velocity leaving the blades is zero, then the air wouldn't be leaving at all. As a result, the air after the blades won't be getting out of the way of the incoming air, and no air flowing through the turbine blades would mean no power. In order to keep the wind moving through the turbine, there has to be some velocity in the air after going through the blades to make way for the incoming air. This is why the machine's efficiency can't be 100%. So according to Mr. Betz's calculations, a perfect wind turbine would be able to convert about 59% of the power in the wind into mechanical rotating power. In practice, this power coefficient ranges between 35% and 45%.

This report does not constitute a rating action.

Primary Credit Analysts:Aneesh Prabhu, CFA, FRM, New York (1) 212-438-1285;
aneesh.prabhu@spglobal.com
Luisina Berberian, Madrid +(34) 91-788-7200;
luisina.berberian@spglobal.com
Sunneva Bernhardsdottir, Toronto + 416 507 3258;
sunneva.b@spglobal.com

No content (including ratings, credit-related analyses and data, valuations, model, software or other application or output therefrom) or any part thereof (Content) may be modified, reverse engineered, reproduced or distributed in any form by any means, or stored in a database or retrieval system, without the prior written permission of Standard & Poor’s Financial Services LLC or its affiliates (collectively, S&P). The Content shall not be used for any unlawful or unauthorized purposes. S&P and any third-party providers, as well as their directors, officers, shareholders, employees or agents (collectively S&P Parties) do not guarantee the accuracy, completeness, timeliness or availability of the Content. S&P Parties are not responsible for any errors or omissions (negligent or otherwise), regardless of the cause, for the results obtained from the use of the Content, or for the security or maintenance of any data input by the user. The Content is provided on an “as is” basis. S&P PARTIES DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING, BUT NOT LIMITED TO, ANY WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE OR USE, FREEDOM FROM BUGS, SOFTWARE ERRORS OR DEFECTS, THAT THE CONTENT’S FUNCTIONING WILL BE UNINTERRUPTED OR THAT THE CONTENT WILL OPERATE WITH ANY SOFTWARE OR HARDWARE CONFIGURATION. In no event shall S&P Parties be liable to any party for any direct, indirect, incidental, exemplary, compensatory, punitive, special or consequential damages, costs, expenses, legal fees, or losses (including, without limitation, lost income or lost profits and opportunity costs or losses caused by negligence) in connection with any use of the Content even if advised of the possibility of such damages.

Credit-related and other analyses, including ratings, and statements in the Content are statements of opinion as of the date they are expressed and not statements of fact. S&P’s opinions, analyses and rating acknowledgment decisions (described below) are not recommendations to purchase, hold, or sell any securities or to make any investment decisions, and do not address the suitability of any security. S&P assumes no obligation to update the Content following publication in any form or format. The Content should not be relied on and is not a substitute for the skill, judgment and experience of the user, its management, employees, advisors and/or clients when making investment and other business decisions. S&P does not act as a fiduciary or an investment advisor except where registered as such. While S&P has obtained information from sources it believes to be reliable, S&P does not perform an audit and undertakes no duty of due diligence or independent verification of any information it receives. Rating-related publications may be published for a variety of reasons that are not necessarily dependent on action by rating committees, including, but not limited to, the publication of a periodic update on a credit rating and related analyses.

To the extent that regulatory authorities allow a rating agency to acknowledge in one jurisdiction a rating issued in another jurisdiction for certain regulatory purposes, S&P reserves the right to assign, withdraw or suspend such acknowledgment at any time and in its sole discretion. S&P Parties disclaim any duty whatsoever arising out of the assignment, withdrawal or suspension of an acknowledgment as well as any liability for any damage alleged to have been suffered on account thereof.

S&P keeps certain activities of its business units separate from each other in order to preserve the independence and objectivity of their respective activities. As a result, certain business units of S&P may have information that is not available to other S&P business units. S&P has established policies and procedures to maintain the confidentiality of certain non-public information received in connection with each analytical process.

S&P may receive compensation for its ratings and certain analyses, normally from issuers or underwriters of securities or from obligors. S&P reserves the right to disseminate its opinions and analyses. S&P's public ratings and analyses are made available on its Web sites, www.standardandpoors.com (free of charge), and www.ratingsdirect.com and www.globalcreditportal.com (subscription), and may be distributed through other means, including via S&P publications and third-party redistributors. Additional information about our ratings fees is available at www.standardandpoors.com/usratingsfees.

Any Passwords/user IDs issued by S&P to users are single user-dedicated and may ONLY be used by the individual to whom they have been assigned. No sharing of passwords/user IDs and no simultaneous access via the same password/user ID is permitted. To reprint, translate, or use the data or information other than as provided herein, contact S&P Global Ratings, Client Services, 55 Water Street, New York, NY 10041; (1) 212-438-7280 or by e-mail to: research_request@spglobal.com.


 

Create a free account to unlock the article.

Gain access to exclusive research, events and more.

Already have an account?    Sign in