25 May 2022 | 14:15 UTC

French nuclear on course for record-low May output, strike planned June 1

Highlights

Output rebounds on Tricastin 2 return

Penly 2 offline unplanned, Cruas 4 delayed

EDF issues 24-hour strike notice for June 1

French nuclear generation remained on course for a record-low May output despite the return of the Tricastin 2 reactor after a five-week refueling outage, system data showed May 25.

Output peaked May 25 at 28.26 GW with May 1-24 averaging 27.55 GW versus 37.20 GW in May 2021.

Over half the French reactor fleet remains unavailable, adding an extra premium to power prices already at record-highs.

EDF's Penly 2 reactor suffered an unplanned outage May 23, while the return of Cruas 4 was delayed by two weeks to June 21, operator EDF said in transparency notes May 24.

French June baseload power was trading May 25 at Eur210/MWh versus a May 24 assessment of Eur177.50/MWh equivalent for UK June baseload power, EEX exchange and S&P Global Commodity Insights data showed.

The 1-GW UK-France ElecLink interconnector started commercial operations May 25 boosting transmission capacity to 4 GW although half of the 2-GW IFA-1 cable remains offline for repairs.

S&P Global Commodity Insights forecast French nuclear to average below 26 GW for the next three months June to August, some 12 GW below the same period last year.

Operator EDF on May 18 again cut its 2022 French nuclear output estimate to a range of 280-300 TWh, the lowest on record for the current fleet with 61.3 GW installed capacity.

EDF also issued a strike notice with unions set to stage another 24-hour strike starting June 1 at 2100 local time (1900 GMT).

FRENCH REACTOR WATCHLIST (summer returns)

Reactor
MW
Outage Start
Scheduled Return
Notes
Tricastin 2
900
16/04/2022
21/05/2022
Refueling
Penly 2
1300
23/05/2022
27/05/2022
Unplanned outage
Cruas 4
900
05/02/2022
21/06/2022
Refueling
Cruas 1
900
14/05/2022
23/06/2022
Refueling
Paluel 4
1300
26/03/2022
29/06/2022
Refueling
St Laurent 2
900
12/03/2022
02/07/2022
Refueling, extra maintenance
Dampierre 4
900
11/04/2022
06/07/2022
Refueling
Gravelines 5
900
16/04/2022
23/07/2022
Refueling
Blayais 3
900
07/05/2022
31/07/2022
Refueling
Chinon 3
900
19/02/2022
07/08/2022
Extra maintenance (SIS check negative)
Chinon 2
900
14/05/2022
07/08/2022
Refueling
Bugey 3
900
29/04/2022
14/08/2022
Refueling (SIS check)
Bugey 4
900
09/04/2022
21/08/2022
Refueling (SIS check)
Tricastin 3
900
12/03/2022
30/08/2022
10-year-overhaul

Source: EDF